Buying a metal building should feel straightforward. To keep it that way, here is a clear walkthrough of how UMB lead times work from quote to installation, what can affect your timeline, and how to prep so your build stays on track.
What does “lead time” actually mean
Lead time is the estimated number of calendar weeks between your order becoming production ready and your installation date window approaching. It accounts for material preparation, fabrication, and scheduling an install crew to your site.
When does the lead start with UMB
Lead times start the moment all three items below are complete.
You approve your building quote.
You pay the deposit noted on your agreement.
Your site is ready with permits and foundation completed.
We require photos of your foundation before we schedule installation. This step helps prevent rescheduling fees and ensures we are on the same page about site readiness since delays can happen.
With our manufacturing headquarters in Rock Falls, Illinois, we build each project to spec in house. Panels are formed and trim is custom cut on state of the art equipment. There is no waiting on overseas vendors for core components.
Our Seasonal Lead Times
Planning ahead helps. These are typical ranges and can vary by state and project size.
Spring: usually under 4 weeks
Summer: 4 to 6 weeks
Fall: 6 to 8 weeks
Winter: usually around 4 weeks
Pro Tip: If you need a faster slot, winter and early spring often provide the most flexibility.
Scheduling Your Building Installation
Once you reach the end of your estimated lead time, our team will contact you about 5 business days before install to confirm a date. During busy months like summer and fall there can be delays. If timing shifts, we will reach out so you’re in the loop.
Most metal buildings install in 1 to 4 days depending on size and foundation type.
Carports and single car garages: about 1 day
Two to three car garages: about 2 to 3 days
Large agricultural or commercial buildings: about 3 to 4 days
What can speed things up
Permits approved before you pay the deposit
Concrete pad cured and documented with photos (please ensure your pad is an adherence to our guidelines)
Clear site access for trucks and trailers
Power availability if your project scope requires it
Quick responses to layout and color confirmations
What can slow things down
Permit review delays at your municipality
Weather that makes the site unsafe
Foundation not poured, not cured, or out of spec
Incomplete or unclear site photos
Change requests after approval
Simple site readiness checklist
Foundation poured, cured, and within spec
Pad swept and free of debris
Grading moves water away from slab
Clear path in and out for delivery and crew vehicles
Nearby materials and obstacles relocated
Pets and livestock secured for crew safety
How we communicate
Order ready: confirmation call or email with your estimated lead window
One week out: call or email to set your installation date
Day before: weather and access double check
During install: on site lead confirms milestones and answers questions
After install: quick walkthrough to ensure everything is up to satisfaction
Ready to start your metal building project with UMB?
If you are set to move forward, choose the path that fits you best.
Use our Dealer Locate form to connect with the nearest UMB dealer for design help and logistics
Build it out in our 3D Builder to visualize colors and options
Request a Quote to work directly with the UMB sales team
We are here to keep your project moving and your schedule clear.